CesTek wins project

Do you have an item that needs to be packed or moved very quickly?

Read here about our latest case as inspiration for a sustainable solution with Omron's NEWEST SCARA robot.

The customer had a breakdown on an existing automation cell for handling and packing items (pick and place).

The spare parts were not immediately available, so we were asked to make an offer for a 1:1 replacement. The packing cell was very energy consuming and also locked in relation to future products on the plant. Therefore, we had to look at solutions for the functions and the cell with new eyes. In collaboration with the customer and Omron, we quickly agreed that the project should include the new SCARA robot type RS4-2054002 combined with completely new IO and control.

  • Cell consisting of pick and place, turners, stackers, and lots of air cylinders - all air supplied by worn out and leaking pneumatic valves and pneumatic cylinders.

  • All other IO cards were based on old ASI bus coding and spare parts were not readily available.

TASK
We were asked to price a 1:1 replacement, which was an energy-intensive investment and very locked in relation to future products on the plant, and we were also asked to come up with new eyes on the functions and the cell - In collaboration with the customer and Omron, we quickly agreed on the profitability of the investment to include the new robot type RS4-2054002. i4-450L, 5 kg payload, 450 mm reach, 4 axis, 180 mm Z axis - combined with completely new IO and control.


Omron  i4 SCARA

Omron i4 SCARA


Solution to customer

  • New mechanical documentation

  • New electrical documentation

  • New control cabinet and operator station

  • Assembly and signal exchange via the new control cabinet with 2x existing machines and special equipment inside the cell

  • Programming of Omron PLC, HMI, Frequency converters and Scara Robot on Ethercat communication

  • New manuals and instructions

  • Testing and commissioning

  • CE marking of the equipment

 


Budget

  • Estimated budget price on proposed solution: 345.000 kr.



Want to know more?

Implementation time was 6 weeks from order placement until production was back in operation.